| OUR PROJECTS > MAJOR PROJECTS > Piping Works |
|
| PROJECT TITLE |
 |
MLNG Rejuvenation and MLNG/MLNG 2 Revamp (MRR) Project - Mechanical Work for Module 2 & 3 |
| |
| SCOPE OF WORK |
- Piping rejuvenation works
- Piping revamp works
- Bad actor valve works
- Motor replacement works
- Static & rotary equipment repair & services
- Fabrication, erection & demolition of steel structure
- Equipment erection works
- Foundation Civil works
- Pre-commissioning & Commissioning
|
| |
| LOCATION : Bintulu, Sarawak |
| CLIENT :Malaysia LNG Sdn Bhd |
| Project Duration :Sept 2003 - August 2005 (23 Months) |
| |
 |
|
| |
|
PROJECT TITLE
|
 |
| Piping Erection Works for Titan No. 2 Cracker Project, Pasir Gudang |
| |
SCOPE OF WORK |
- Erection of 90,000 I.D. piping work in Process Plant
- Fabricate & install 90 tonnes of pipe supports
- NDT Inspection
- Hydrotesting
- Precommissioning & commissioning
|
| |
LOCATION : Titan Petrochemical, Pasir Gudang, Johor |
| CLIENT : JGC Corporation |
|
DURATION : Mar 1998 - Feb 1999 (11 Months) |
|
| |
| ^ back to top ^ |
|
PROJECT TITLE
|
 |
| Piping Work for LRCCU Crude & Bitumen Tank Farm |
| |
SCOPE OF WORK |
- Fabricate and erect 45,000 I.D. piping
- Civil works including pipe sleepers and road crossings
- Fabricate and erect of 11,000m of steam tracing.
- Fabricate and erect of 100 tonnes of steel structure.
- 27 process tie-ins and 10 firewater tie-ins
- Demolish 50 tonnes of existing pipeline and structure
- Blast and paint all piping
- Insulation works
- Equipment installation works
|
| |
LOCATION : Shell Refinery, Port Dickson |
| CLIENT : Shell Refining Company (FOM) Bhd |
DURATION : Nov 1996 - Sept 1997 (11 Months) |
| |
|
|
| |
| ^ back to top ^ |
|
PROJECT TITLE
|
 |
| Piping Works for Polypropylene Plant, Its Utilities and Offsite Facilities at Kuantan, Pahang |
|
| SCOPE OF WORK |
- Fabricate & erect onsite & offsite piping work (80,000 I.D. carbon steel & 20,000 I.D. stainless steel)
- Fabricate & install 80 tonnes of pipe supports
- Assits in commissioning and start-up
|
| |
LOCATION : Polypropylene Malaysia, Kuantan |
| CLIENT : Toyo Engineering Corporation |
DURATION : 12 Months |
|
| |